Nuclear Reactor In Southwestern Japan Goes Offline


Nuclear reactor in southwestern Japan goes offline

The operator of a nuclear power plant in southwestern Japan has suspended one of its reactors as it cannot meet the deadline for building mandatory facilities to deal with emergencies.

Kyushu Electric Power Company began work to reduce output at the No.1 reactor at the Sendai plant in Kagoshima Prefecture at 2:30 a.m. on Monday. The reactor went offline at 1:01 p.m.

Kyushu Electric will start regular inspections on the reactor earlier than scheduled.

This is the first time for a reactor to go offline because of its failure to meet the government's new regulations.

The regulations were drawn up in 2013 after the nuclear accident at the Fukushima Daiichi plant two years earlier.

They require nuclear plant operators to construct facilities to ensure the safety of reactors in the event of emergencies such as acts of terror and aircraft crashes.

The Nuclear Regulation Authority, or NRA, obliges the operators to erect such facilities within five years of construction plans being approved.

Kyushu Electric says it aims to put the reactor back online after completing the necessary facilities by December and gaining approval from the NRA.

The utility also plans to shut down the No.2 reactor at the Sendai plant in May for failing to meet the deadline.

Kansai Electric Power Company is also expected to suspend the No.3 and No.4 reactors at the Takahama nuclear plant in Fukui Prefecture in August and October respectively for the same reason.